CDM 2015 for small contractors: the construction phase plan, the notification thresholds, and how project software keeps the record

HSE says a construction phase plan is required for every construction project under CDM 2015, and projects over set thresholds must be notified to HSE. A job can cross the second threshold by total worker days without ever having 20 people on site. Software can keep the plan, the headcount and the inductions together for every job, but a competent person must identify the hazards and judge what has changed.
The short answer
Under the Construction (Design and Management) Regulations 2015, HSE says “a construction phase plan is required for every construction project”, however small. For a typical small job the plan can be short, but it must exist before the work starts, and larger jobs have an extra duty: notification to HSE once they pass set thresholds.
For a contractor with many jobs running at once, that is a record-keeping problem repeated on every site. A project system can hold a plan for each job, keep who is on site and who has been inducted, and warn when a job is heading towards the notification thresholds. It cannot decide what the hazards on a site are or whether the plan still fits the work. A competent person does that.

The plan that every job needs, and how short it can be
HSE’s leaflet for small builders, CIS80, is direct about the scale of it: “A simple plan before the work starts is usually enough to show that you have thought about health and safety.” It gives examples of small-scale routine work, including installing a kitchen or bathroom, roofing work and loft conversions, and lists what to write down:
- Key dates: start and finish, and when services will be connected or disconnected.
- Information from the client, such as where the services and isolation points are, access restrictions and whether there is any asbestos.
- Who else is working on the job, with contact details, and how you will communicate and coordinate with them.
- The main dangers and how they will be controlled, with toilet, washing and rest facilities.
- A named person responsible for the job running safely, and how supervision will be provided.
Each of these is a field on a job. None of them is hard. The difficulty is that there is one set per site, they are needed before the work starts, and they change when the work does.
Who has to do what: client, principal contractor, contractor
CDM 2015 spreads the duties across the people on a project, and the HSE pages set out each role. The ones that create paperwork for a contractor are these:
- The principal contractor must “prepare a written construction phase plan before the construction phase begins, implement, and then regularly review and revise it to make sure it remains fit for purpose”. They must also make sure workers have site-specific inductions and that welfare facilities are provided from the start.
- A sole contractor has the plan duty too: “Where a contractor is the only contractor working on a project, they must ensure a construction phase plan is drawn up before setting up the site.”
- Every contractor must “make sure the client is aware of the client duties under CDM 2015 before any work starts”, and on multi-contractor jobs must comply with the parts of the plan that apply to their work.
- A commercial client must “provide pre-construction information to every designer and contractor either bidding for the work or already appointed to the project”, and make sure the plan is prepared before the phase begins.
With a domestic client, the principal contractor normally takes on the client duties as well. If no principal contractor is appointed, HSE says the contractor in control of the construction phase carries out that role. For a small firm, that can mean holding several sets of duties on one job.

Notification: the thresholds a job can cross without anyone noticing
HSE defines a notifiable project as one “where planned construction work will last longer than 30 working days and involves more than 20 workers at any one time; or where the work exceeds 500 individual worker days”. For those, a commercial client must notify HSE in writing and “ensure a copy of the notification is displayed in the construction site office”. HSE’s page on how to notify points to the online F10 form.
There are two separate tests, and the second is the one that surprises people. A job does not need 20 people on site at once to cross it. Twelve workers for 45 working days is 540 worker days, which exceeds 500, and the project is notifiable even though there were never more than 12 people there. HSE’s leaflet adds that a job above those levels “is likely to be too complex for this simple plan format”.
That makes the planned headcount and duration worth recording at the quote stage, not after the job has grown. A scope change that adds labour can move a job across the line without anybody deciding that it should.
Why the plan is worth the effort
The HSE fatal injury statistics are a reminder of what the regulations are for. Construction recorded more worker deaths than any other single industry in 2025/26.
These are provisional figures for a whole industry, not for projects covered by CDM 2015 specifically, and they say nothing about any single firm. In HSE’s figures for the same year, falls from a height were the most common kind of fatal accident across all industries, at 31 deaths. The leaflet’s first example of a danger to plan for is working at height, which it ties to the need for scaffolding.

What software can do, and what it cannot
This is project-record work, repeated for every site. The chart below uses illustrative figures, not client data, for a contractor with about 25 live jobs.
Illustrative inputs, not client data. Totals: 40 hours a month by hand against 17 with a system. Reviewing and revising a plan falls least, on purpose: someone who knows the site decides what has changed and what it means. A system removes the retyping, collecting and threshold-checking, not the judgement. Substitute hours you have measured.
Show the data
| By hand | With a system | |
|---|---|---|
| Writing or adapting a construction phase plan for each job | 12 hrs | 5 hrs |
| Collecting site inductions and who-is-on-site records | 10 hrs | 3 hrs |
| Checking each job against the notification thresholds | 4 hrs | 1 hrs |
| Chasing the client for asbestos, services and access information | 8 hrs | 4 hrs |
| Reviewing and revising plans when the work changes | 6 hrs | 4 hrs |
The shape matters more than the figures: retyping a plan for each job, collecting inductions and checking thresholds is mechanical, while deciding what has changed on a site is not. A projects and delivery system with milestone planning, task boards and time tracked against budget can hold each job’s plan beside its programme. Used well, it can:
- Start every job from a plan template with the fields above, so the plan exists before the first day on site.
- Hold planned dates, headcount and tracked time, and flag a job heading towards 30 working days, 20 workers at once or 500 worker days.
- Record who is on site and who has been inducted, captured on a phone with the forms and signatures in field service and mobile.
- Keep the evidence with the project for audits and client requests, using the registers and evidence packs in compliance and certification.
- Price and record changes so that a scope change that adds labour is visible, and a variation is not lost. See project variations.
What it cannot do is identify the hazards on a particular site, decide whether a job is notifiable in a borderline case, or appoint a principal contractor. Those are decisions for a competent person. Our installer platform is built on one shared record per job, and the specifics are set in an assessment visit. For related admin, see field service software for installers and MCS installer job management.

Where to start this week
- Pick three live jobs and ask whether each has a written construction phase plan, dated before the work started.
- Check each job’s planned duration, peak headcount and total worker days against the two notification tests.
- Write one short plan template from the CIS80 headings, and use it for the next job.
- Check who holds the client information on services, access and asbestos, and when you get it.
- Test one job: could you show, today, who is on site, who has been inducted and who is responsible?
This is general information based on the HSE pages and leaflet as we read them on 4 November 2026. The HSE CDM pages carry no publication date, so check the current position. We have not covered the regulations themselves, HSE’s detailed guidance, the F10 form or penalties, and this is not legal advice.
Frequently asked questions
Does every construction job need a construction phase plan?
HSE says a construction phase plan is required for every construction project under CDM 2015, and that it does not need to be complicated. For small-scale routine work such as a kitchen or bathroom installation, roofing or a loft conversion, HSE's busy-builder leaflet says a simple plan before the work starts is usually enough to show that you have thought about health and safety. Larger or notifiable jobs are likely to be too complex for that simple format.
When does a construction project have to be notified to HSE?
HSE describes a notifiable project as one where the planned construction work will last longer than 30 working days and involves more than 20 workers at any one time, or where the work exceeds 500 individual worker days. For notifiable projects a commercial client must notify HSE in writing and make sure a copy of the notification is displayed in the construction site office. A job can meet the second test without ever having 20 people on site: 12 workers for 45 working days is 540 worker days.
Who has to prepare the construction phase plan?
HSE says the principal contractor must prepare a written construction phase plan before the construction phase begins, then implement it and regularly review and revise it. Where there is only one contractor, that contractor must ensure a plan is drawn up before setting up the site. A commercial client must ensure the plan is prepared before that phase begins. When working for a domestic client, the principal contractor or sole contractor normally takes on the client duties as well as their own.
What should a simple plan record?
HSE's busy-builder leaflet lists key dates, information from the client such as where services and isolation points are, access restrictions and any asbestos, who else is on site with their contact details, how you will communicate and what you will do if the plan or materials change, the main dangers and how they are controlled, welfare facilities, the person responsible for the job running safely, and how supervision is provided.
Do these rules apply in Northern Ireland?
The HSE pages say CDM 2015 came into force in Great Britain on 6 April 2015, and this article covers only the HSE guidance for Great Britain. We have not reviewed the arrangements in Northern Ireland, so check them separately if you work there.